Construction Dispute Investigation

SCHEDULE OF BASE BID ITEMS
Base Bid Items Project Total Completed
Environmental Requirements: Erosion sedimentation, dust, noise controls. $1,000 $400
Remove Existing:  
a. Concrete steps, walks, pads, and landings 3,000 2,000
b. Water line 1,400 1,400
c. Utility poles 300 ---
d. Bitumen & gravel pavements and stockpile gravel for reuse 1,190 1,190
e. Existing foundation 1,000 1,000
f.  One story wood house & concrete foundation 2,000 ---
g. Three story brick building & concrete foundation 15,000 ---
Relocate: Basketball goals with new supports, posts, and concrete 1,000 ---
Excavation & Grading:
a. Strip and grub site 1,760 600
b. Cut and fill 4,550 4,000
c. Granular Borrow, to Building Floor S. G. 22,400 7,000
d. General site grading 1,500 ---
e. Ground water controls 1,000 400
f. Protect existing utilities 1,000 400
Ledge Excavation – Per Contract Allowances: 
a. Open ledge 9,000 ---
b. Trench ledge 12,000 13,184
Excavation/Backfilling – Extension Utilities:
a. Flag pole base 200 ---
b. 4" water line 1,200 1,200
c. 12" rain water to catch basin 350 ---
d. Underground – electric & telephone 1,920 1,920
Furnish & Install – Exterior Storm Systems:  
a. Adjust existing manhole 500 3,000
b. New culverts: 8" A C P &  12" A C P 3,700 1,500
c.  New catch basin (4' - 6") 2,000 2,000
d. Subdrains: 4" perforeted or bitumen 6,720 600

- -Fittings: 4" x 4" wyes

300 ---
- -4" x 90/45 bends
400 ---
e.   Excavations for above 2,400 400
f.  Backfills for above: (Sand) 300 200

- -Underdrain materials

500 200

- -Excavation materials

600 200
g. Pumping 1,000 600
Furnish and Install: 
a. Box guard rail 3,500 ---
b. Granite curbs: straight 8,400 ---

- -Radius

9,200 ---

- -Curb ends

2,000 ---

- -Continuous concrete backfill at both sides of curbing

2,040 ---
c. Chain link fence @ LP gas pad 1,600 ---
3' C. L. gate 600 ---
Furnish, place, grade, and compact gravel for: --- ---
a. Walks - (3" material) x 6" depth 2,240 ---
b. Drives, shoulders, parking: (3" - material) x 12" depth 26,400 16,000
Building Items:
a. Excavations for: foundation walls/footings, pits, trenches 6,600 6,600

- -Underfloor piping

1,840 ---
b. Backfills, for above: --- ---

- -1. Select material - INSIDE

7,200 2,400

- -2. Common material - OUTSIDE

3,200 1,200

- -3. Compactions - INSIDE

600 200
c. Furnish, place, grade, and compact; Gravels under slabs: (3" - material) x 6" depth 2,940 ---
d. Gravel drip strips: --- ---

- -1.3" stone

700 ---

- -2. *" x 5" Metal retainer

1,000 ---

- -3. 16" stakes

240 ---
Landscape Items:
a. Submit loam sample 200 ---
b. Spread loam, prepare for seed 10,400 ---
c. Seed and mulch 2,800 ---
d. Care, maintenance, guarantee 400 ---
Engineering/layout, for above: 5,000 3,000
From Building Lines, grades, layout, established by G. C. --- ---
TOTALS $200,290 $72,794