Construction
Dispute Investigation
|
STATEMENT OF MONIES DUE DANIELS TRUCKING
|
||
| Value of work completed by Daniels Trucking |
74,794.00 |
|
| Deductions | ||
| Site Prep.s portion 20% x $74,794.00 = |
14,958.00 |
- |
| Payments on Requisition #1 |
21,696.00 |
- |
| Payments on Requisition #2 |
10,000.00 |
- |
|
Total deductions: |
46,654.00 |
- |
| Amount owed on work performed = $74,794.00 - $46,654.00 = |
28,140.00 |
|
| Reimbursement for Fine Grading |
300.00 |
|
| Reimbursement for Soil Testing |
3,452.04 |
|
| Reimbursement for Hand Labor for cleaning ledge in foundation trenches 140 hrs. @ $11.50 |
1,610.00 |
|
|
Total Due: |
$33,502.04 |
|