Construction Dispute Investigation

DIARY
---
Start - May 30, l998 -
June 1 - June 15

Stripping parking lot areas and building site area. On the second week, started hauling gravel. Digging out old foundation with the 880.

June 15 - June 30

Trenching for foundations; hauling gravel to parking lot. Demolished canopy and front steps. Continued to dig out old foundation. Uncovered ledge at foundations. Blasting all ledge.

July 1 - July 15

Removing ledge and redigging trenches for foundation with 880. Went back to old foundation and loaded trucks. Dug drainage ditch. Installed 12’ culvert, using hand labor to clean trenches. Dug for U.G. electrical conduit.

July 15 - July 30

Installed underdrain. Installed MH. Hired Phillip Smith to haul in gravel for parking lot.

Aug. 1 - Aug. 15

Smith hauling gravel for inside building. Got parking lot area ready for paving (compacting, graveling, etc.) Jackhammering for waterline.

Aug. 15 - Aug. 30

Dug for waterline and did jackhammer work on ledge. Parking lot fine-graded and paved. R. Daniels hauling gravel for inside building. Smith also hauling. Backfilling and compacting gravel inside the building and outside around foundation walls. Placed about 800-1000 cy

Off job - Sept. 5 -